Design basis
Confirm GPU model, OEM cooling envelope, peak and sustained IT load, site weather and supply interfaces.
ALICE™ PMDC · ENGINEERING
Design studies are not certified product ratings. All gates require project evidence before release.
Confirm GPU model, OEM cooling envelope, peak and sustained IT load, site weather and supply interfaces.
Verify usable internal dimensions, maintenance clearances, door swing, equipment removal, wet mass, lifting and anchorage.
Separate technology and facility loops; verify fluid properties, flow, pressure loss, CDU approach, dew point, ambient design conditions and residual air cooling.
Confirm voltage, power factor, fault level, protection coordination, grounding, UPS autonomy and capacity after a component failure. A/B feeds alone do not establish 2N.
Obtain OEM warranty and fluid compatibility evidence; assess tank wet mass, containment, fire risk, lifting, fluid ageing and disposal.
Agree test loads, duration, inlet limits, flow, alarm thresholds and failure/recovery scenarios before testing; record measured results and exceptions.
Engineering references:OCP Cold Plate · OCP Immersion · ASHRAE Data Centers · The Green Grid PUE
Rack counts are arithmetic requirements, not physical fit. Tank symbols represent quantity only.
Water flow uses 1,000 kg/m³ and 4.186 kJ/(kg·K). Use actual fluid properties and pressure losses for pump selection.
A dry cooler alone is feasible only when design ambient temperature, required supply temperature and heat exchanger approaches permit it.